Sample 60-Point Factory Audit Report
The 60-point on-site factory audit format we use in India: legal checks, capacity, machinery, quality, social compliance and export readiness, with a scored conclusion.
Sample format. The factory, order and figures on this page are illustrative and do not describe a real company or client. Your report follows this structure, with photos, videos and document copies from your supplier.
- Factory
- Sample Knits Pvt. Ltd. (fictional)
- Location
- Tiruppur, Tamil Nadu, India
- Product
- Cotton jersey T-shirts, private label
- Audit type
- Pre-order on-site factory audit
- Auditor
- Gulshan Marwah team (on site, 1 day)
- Evidence
- 142 photos, 6 videos, document copies
51 / 60
Pass8 / 60
Observation1 / 60
Fail1. Legal existence & registrations
| # | Check | Finding | Result |
|---|---|---|---|
| 1 | Company registration (CIN / LLPIN) checked on the MCA portal | Private limited company, active, incorporated 2009 | Pass |
| 2 | GSTIN active on the GST portal, name and address match | Active, regular filer | Pass |
| 3 | IEC verified on the DGFT portal | Active, matches company PAN | Pass |
| 4 | Udyam (MSME) registration | Medium enterprise | Pass |
| 5 | Factory licence under the Factories Act | Valid, renewed this year | Pass |
| 6 | Pollution Control Board consent to operate | Valid; dyeing done by an outside unit | Pass |
| 7 | Audited address is the registered or declared works address | Matches GST and IEC records | Pass |
| 8 | Owners / directors identified and met in person | Managing director met on site | Pass |
| 9 | Bank account in the company name | Cancelled cheque matches company name | Pass |
| 10 | Public records: litigation, insolvency, defaults | Nothing adverse found | Pass |
2. Facility & capacity
| # | Check | Finding | Result |
|---|---|---|---|
| 11 | Site area, ownership or lease | Owned building, 3 floors | Pass |
| 12 | Production lines counted on the floor | 9 stitching lines running | Pass |
| 13 | Workers on shift counted | About 310 on day shift | Pass |
| 14 | Declared monthly capacity against what we observed | Declared 180,000 pcs; observed output supports about 150,000 | Observation |
| 15 | Current order book and free capacity in your delivery window | About 35% free in the requested month | Pass |
| 16 | Subcontracting declared (printing, dyeing, embroidery) | Dyeing and printing outsourced, units named | Observation |
| 17 | Raw-material and finished-goods storage | Racked, dry, separated by order | Pass |
| 18 | Power backup | Two diesel generators | Pass |
| 19 | Housekeeping and floor organisation | Good | Pass |
| 20 | Quoted lead time is realistic | 45 days quoted; 50–55 days more realistic | Observation |
3. Machinery & process control
| # | Check | Finding | Result |
|---|---|---|---|
| 21 | Key machines listed with make and age | Single-needle, overlock and flatlock machines, mostly under 8 years old | Pass |
| 22 | Maintenance records | Maintained, monthly log | Pass |
| 23 | Measuring instruments calibrated | Two measuring tapes out of calibration date | Observation |
| 24 | Process flow documented for the product | Documented and displayed | Pass |
| 25 | Cutting room: marker planning and fabric relaxation | CAD markers; 24-hour relaxation followed | Pass |
| 26 | Needle control and metal detection | Needle log kept; no metal detector on the packing line | Fail |
| 27 | Ownership of patterns, screens and tooling | Buyer-owned patterns held separately | Pass |
| 28 | Sampling room and development capability | Sample room with 6 machines | Pass |
| 29 | Technical staff and supervisors | Production manager, 2 merchandisers, line supervisors | Pass |
| 30 | Production planning and tracking | Spreadsheet plan, updated daily | Pass |
4. Quality management
| # | Check | Finding | Result |
|---|---|---|---|
| 31 | Independent quality-control team and headcount | 14 QC staff reporting to the QA manager | Pass |
| 32 | ISO 9001 or similar certificate | ISO 9001 valid; certification body confirmed | Pass |
| 33 | Incoming fabric and trims inspection | 4-point fabric inspection recorded | Pass |
| 34 | In-line inspection records | Hourly checks on every line | Pass |
| 35 | Final inspection to AQL before shipment | AQL 2.5 used for export orders | Pass |
| 36 | In-house testing equipment | GSM cutter and shrinkage test; colour fastness sent out | Observation |
| 37 | Defect records and corrective actions | Kept, but corrective actions are not closed out | Observation |
| 38 | Traceability by lot and bundle | Bundle tickets traceable to line | Pass |
| 39 | Customer complaint handling | Log kept for the last 12 months | Pass |
| 40 | Approved (golden) sample control | Sealed samples kept at each line | Pass |
5. Social compliance, safety & environment
| # | Check | Finding | Result |
|---|---|---|---|
| 41 | Minimum wages (payroll sample of 10 workers) | At or above the state minimum | Pass |
| 42 | PF and ESI registration and payments | Registered, recent challans seen | Pass |
| 43 | Working hours and overtime records | Overtime within legal limits, paid at double rate | Pass |
| 44 | No child labour: age records checked | Age proof on file; no under-age workers seen | Pass |
| 45 | Fire NOC, extinguishers, marked exits, drills | Valid NOC; one exit partly blocked by cartons | Observation |
| 46 | First aid and personal protective equipment | First-aid boxes stocked; metal gloves in cutting | Pass |
| 47 | Electrical safety | Panels covered and labelled | Pass |
| 48 | Toilets, drinking water and canteen | Adequate and separated by gender | Pass |
| 49 | Waste and effluent handling | Fabric waste sold to an authorised recycler | Pass |
| 50 | Grievance mechanism and workers committee | Committee in place, suggestion box | Pass |
6. Export readiness
| # | Check | Finding | Result |
|---|---|---|---|
| 51 | Export history (shipping bills, last 12 months) | 38 shipments to the EU, UK and the US | Pass |
| 52 | Main export markets and buyers named | Mid-size European retailers | Pass |
| 53 | RCMC with the relevant export promotion council | AEPC RCMC valid | Pass |
| 54 | Export packing standard (cartons, polybags, warnings) | 5-ply cartons; suffocation warnings printed | Pass |
| 55 | Labelling and GS1 barcode capability | Prints labels in house; buyer GS1 codes used | Pass |
| 56 | Certificates for the target market | OEKO-TEX Standard 100 valid; GOTS not held | Observation |
| 57 | Export documents: invoice, packing list, certificate of origin | In-house documentation team | Pass |
| 58 | Payment terms accepted (L/C, T/T, D/P) | L/C at sight and 30/70 T/T | Pass |
| 59 | English-speaking contact for the buyer | Merchandiser fluent in English | Pass |
| 60 | Buyer references that can be contacted | Two references given | Pass |
Conclusion
Approved with conditions
A genuine, export-experienced factory with the capacity for the order. Before production: install or hire a metal detector for the packing line, clear the blocked fire exit, and plan for a 50–55 day lead time. We recommend a pre-shipment inspection at AQL 2.5.